ISMILESTONE

ISMILESTONE(type)

TRUE when a task's Type is a milestone: a start milestone or a finish milestone. A milestone takes no time, so a rule about durations, resources or progress usually leaves milestones out, and a rule about contract dates usually looks only at them. To tell the two apart, compare the Type itself: [Type] = "Start milestone".

Arguments

ArgumentWhat to give it
typeA task's Type: [Type], or the Type column of a set, like Successors[Type].

Examples

Formula
=ISMILESTONE([Type])

TRUE on every start and finish milestone.

Formula
=IF(NOT(ISMILESTONE([Type])) AND INDAYS([Duration]) > 20, "Too long", "")

Flags the activities longer than 20 days, leaving the milestones out.

Formula
=COUNT(FILTER(Successors, ISMILESTONE(Successors[Type])))

How many of the task's successors are milestones.

Reach for something else when

You wantUse
Only the start milestones, or only the finish ones[Type] = "Start milestone", [Type] = "Finish milestone"
The tasks with no duration, whatever their type[Duration] = 0d

Common questions

What is the difference between a start and a finish milestone?

A start milestone marks the start of something, such as Notice to Proceed: it is dated at the start of the working day its predecessors let it start on. A finish milestone marks something done, such as Substantial Completion: it is dated at the finish of the work before it, on the same day.

Why does [Type] = "Milestone" give an error?

There is no Type called Milestone: a milestone is a Start milestone or a Finish milestone. ISMILESTONE([Type]) is TRUE for either.